History & communities

The Flathead Tunnel and the railway Libby Dam displaced

How the Libby Dam project rerouted the historic Great Northern mainline and led to construction of a seven-mile rail tunnel in the Salish Mountains.

Part of the old railway north of Jennings lay in the footprint of Lake Koocanusa. The Libby Dam project replaced it with a new alignment between Jennings and Stryker, including the roughly seven-mile Flathead Tunnel.

A new mainline above reservoir country

The U.S. Army Corps of Engineers described the replacement as about 60 miles of new route. Its project statement calls the line Burlington Northern, while its retrospective project history identifies the displaced route with the Great Northern Railway. The seven-mile tunnel through Elk Mountain in the Salish Mountains was one part of a much longer relocation.

From excavation to train service

A U.S. Bureau of Mines study dates the start of tunnel excavation to September 1966 and its completion to June 1968. President Lyndon B. Johnson took part remotely in the June 21, 1968 ceremony marking the breakthrough. The Bureau of Mines records the last concrete lining work in June 1969 and places the tunnel in service in November 1970.

These milestones answer different questions about the same project. The breakthrough joined the two excavation headings. Work still had to make the passage ready for trains. The Bureau of Mines report explains that work and the difficulties engineers had supporting and lining the bore.

Sources